The house is finished, but the project is not. These steps make it legally occupiable, insurable, and sellable.

1. Compliance Certificate, then Occupation Certificate

This is two steps, not one, and there is a deadline between them that catches people out.

Section 19 of the Building Control Act 2012: "where a building has been erected after obtaining a permit, that building shall not be inhabited, used or occupied unless a compliance certificate has been issued by the local authority which issued the permit."

The sequence:

  1. Inform the local authority when construction starts. A letter format is provided in the BLP Guide (page 60). This is an obligation, not a courtesy.
  2. Inform the local authority when construction is complete (format at page 61 of the same guide).
  3. Inspectors visit the site and check the building has been "completed within acceptable norms in line with approved plans".
  4. The compliance certificate is issued — the guide states it "should be issued within 5 working days of the application".
  5. Apply for the Occupation Certificate within 5 days of obtaining the compliance certificate, and before occupying or using the building.

🚨 You may not legally inhabit, use, or occupy the house until this is done. Plan your move-in date around it, and do not let a landlord's notice period or a lease ending force you into occupying early.

⚠️ Note the compliance certificate form in the guide is headed "for buildings above 150m²". Confirm with your own local authority what applies to a house below that area — practice varies between municipal and district councils.

⚠️ VERIFY — Fees for the compliance and occupation certificates are not stated in the BLP guide. Confirm current fees and the exact document list with the local authority that issued your BLP.

Also note: your BLP is only valid for 2 years from the date of issue (Section 18(1), Building Control Act 2012). If your build stalls, check the expiry — see Building and Land Use Permit (BLP).

This is where unauthorised changes come back to bite you. The inspection is explicitly against the approved plans. If the house as built differs — an extra room, a covered terrace, a reduced setback — the certificate can be refused until it is regularised. Regularising afterwards is far harder than getting a variation approved during the build. See Building and Land Use Permit (BLP) and Choosing a Contractor.

2. Utility Connections

Most utilities require the BLP, and some require the Occupation Certificate.

3. Municipal / District Council Records

4. Insurance

5. Claim Your Refunds and Grants

Do not leave money unclaimed. Several schemes are claimed after completion and have deadlines.

⚠️ Scheme conditions, ceilings, and deadlines change with each annual Budget. Confirm what currently applies with the MRA before assuming eligibility.

6. Keep Your Project File

Keep everything together, and keep a digital backup. A future buyer, bank, or insurer will ask for it.

7. The Defects Liability Period

For the agreed period after handover — commonly 6 to 12 months — the contractor must fix defects at their own cost.

⚠️ Important Note

🚨 Do not release the retention early because the contractor asks nicely. The first cyclone season and the first heavy rains are the real test of the roof, the waterproofing, and the drainage. Wait them out.