The Construction Phases

Facts last checked 0 of 74 checklist items done

The Construction Phases

What actually happens on site, in order, and what to check at each stage before it is covered up. Concrete and plaster hide everything. Once a stage is buried, your only options are trust or demolition.

Your architect should inspect and certify each stage before you release payment — see Choosing a Contractor.

Before Work Starts


1. Site Setting Out and Excavation

The building is marked out on the ground and foundation trenches are dug.

Check before proceeding:

2. Foundation

Footings, reinforcement, and concrete.

Check before the concrete pour — this is your last chance:

3. Columns, Ground Beams, and Backfilling

Check:

4. Walls / Blockwork

Check:

5. Roof Slab Casting

The biggest single pour of the project, and a milestone with real consequences — the roof slab grant in Government Schemes, Refunds and Grants relates to this stage.

Check before the pour:

⚠️ Do not let props be removed early to speed the next stage. The concrete has not reached strength.

6. Plumbing and Electrical Rough-In

Pipes and conduits are chased into walls and slabs before plastering.

Check before plastering closes it all in:

7. Plaster, Screed, and Waterproofing

8. Finishes

Tiles, doors, windows, joinery, sanitary ware, painting, kitchen.

9. Externals

Frequently excluded from the main contract — confirm with your contractor.

10. Snagging and Handover

Before the final payment, walk the house with your architect and write a snag list.

Then proceed to After Completion.

⚠️ Important Note

🚨 The single most valuable habit on site: photograph every stage before it is covered. Reinforcement before concrete, conduits before plaster, foundations before backfill. It costs nothing, and it is the only evidence you will ever have.