CWA — Water

Facts last checked

CWA - Domestic New Supply

Documents needed:

  • Title Deed — copy plus the original, which is returned after verification
  • Copy of National ID Card of applicant/Proxy/Landlord/Owner/Heirs
  • 2 Copies of Site/Location plan
  • Building and Land Use Permit — see Building and Land Use Permit (BLP)

If you are not the owner:

  • Letter of Authorisation from the owner, plus the owner's ID card
  • Tenants also need the rent book

Fees

ItemAmount
Processing fee (non-refundable)Rs 500
Installation feeRs 2,200 over and above the processing fee

⚠️ Budget Rs 2,700, not Rs 500 — the installation fee is charged in addition. Long connections from a distant main may cost more; confirm with CWA. See Financing Your House.

Application form: https://cwa.govmu.org/cwa/wp-content/uploads/2022/12/Application-for-New-Water-Supply.pdf Source: https://cwa.govmu.org/cwa/?page_id=743